Project Details

CLIENT: Associated British Ports
LOCATION: Southampton Docks
START DATE:  
COMPLETION DATE:
VALUE:  
  • Installation of new reinforced Concrete Passenger walkway foundations.
  • Decommissioning, Demolition of existing walkway structure and Foundation, making good external cladding and internal decoration of QEII Terminal once existing walkway removed
  • Installation of 30 number 450mm x 16m deep reinforced augured Piles within 10m of Quayside.
  • Diversion of quayside watermain inclusive of pressure testing and chlorination
  • Installation of new drainage & associated catch pits
  • Installation of Reinforced concrete running beam
  • Supply and installation of new walkway running track – 90m in length.
  • Reinforced concrete works to quay side
  • Works carried out while quayside operational, working closely with ABP Berth planning department.