Basingstoke Sub-Station

Project Details

CLIENT: SSE
LOCATION: Basingstoke
START DATE: 06/2007 
COMPLETION DATE:  02/2008
VALUE:  £802,000
  • Earthworks to compound consisting of upper/mid/lower terraces 900m³
  • Sheet piled retaining wall 700m² with 110m of concrete capping beam
  • Concrete access road at upper level with link to existing road – 620m²
  • Transformer & Cooler bunds with specialist acoustic enclosures
  • Concrete bases for electrical equipment
  • Traditional masonry block & brick switch houses with reinforced concrete cable basements; steel sheet roof
  • New steel palisade security fencing & new entrance gates
  • Installation of concrete cable troughs and ducting to all levels
  • Provision of drainage
  • 4500m³ of compacted stone surfacing